Redondo Beach has stopped trying to remake its waterfront in one giant project. It now fixes King Harbor one piece at a time: a sign, a lot, a lease, a pool. The council approves each one on its own, often in a single unanimous vote. This fall several of those pieces show up at once, and together they show both what the approach delivers and what it gives up.
The Plan That Froze the Boardwalk
The clearest example of the old approach is at 123 International Boardwalk. In 2017, the City Council was set to buy the Redondo Fun Factory back from its owner to clear the way for a massive redevelopment of the entire waterfront, according to the Daily Breeze. That redevelopment fell apart. While court disputes over it dragged on, the city couldn't renegotiate the arcade's lease.
Two years later, in October 2019, the Fun Factory closed after nearly five decades of Skee-Ball, carnival games and a Tilt-A-Whirl that had spun riders since 1972 for as little as 50 cents a ticket. The Fun Fish Market & Restaurant next door closed with it. The space has been vacant ever since.
Seven years of an empty storefront is what tying everything to one master plan cost. What came next was smaller.
The Arch at the Harbor Entrance Goes First
The King Harbor gateway sign has stood at the marina entrance with few changes for nearly 60 years. In December 2025 the council approved a new design. On August 4, 2026, it hired San Pedro Sign Company to build and install the replacement. The contract was on the consent calendar, the list of routine items approved in one vote. Work was scheduled to start in August and finish by November, the Daily Breeze reported.
The new sign keeps the arch. The lettering changes from the serif type it has carried for decades to a sans-serif font. The city's newest logo replaces the sailboat in the center seal, which has been repainted many times over the years. Mayor Jim Light had described rusting metal, faded colors, cracked and peeling paint, and aging plastic. The poles get repainted, and everything else is new.
The cost shows how the project grew. The city's 2025-26 Capital Improvement Program set aside $74,000 to repaint the sign. Full replacement costs $158,786, a bit more than twice that, with money also coming from the 2026-27 budget. Even at twice the original budget, it's a modest project, paid for and voted on separately, with nothing else waiting on it.
A Bowling Alley Waits on a Lease
The Fun Factory is moving the same way. In 2024 the council approved earthquake retrofits for the building and filling in the pit where the Tilt-A-Whirl used to sit. Once that work was done earlier this year, the city started looking for tenants.
On July 21, again on the consent calendar, the council approved an exclusive negotiating agreement with Multiverse, which operates Level Up Bowl and Bistro. The plan is a bowling alley, an arcade, a bistro-style restaurant and a sports bar. Level Up recently opened a similar venue at The Avenues mall in Rolling Hills. "I am excited to bring something new, exciting, locally owned and family-oriented to this space," Light wrote on Facebook, as quoted by the Daily Breeze.
The agreement is a structured courtship, and it doesn't commit the city to a lease. The council's agenda file sets a 60-day due-diligence period, extendable by 30 days, then up to 60 days of lease talks, also extendable by 30. If every extension is used, the window runs about six months from the July vote, into January 2027. The space was also built as part of the pier parking structure, so a city staff report says it would need significant study before anyone can say how much of it can be rebuilt.
The Park Pointed at the Power Plant
At the north end of the harbor, the piecemeal approach has already delivered something you can walk through. Bill Brand Gateway Park opened July 28 at the southwest corner of Herondo Street and Pacific Coast Highway, on land under Southern California Edison power lines that had long been a dirt lot. The Daily Breeze called it the city's first new green space in at least a decade.
So far, about half of the 5.1-acre site is park. It has native plants, a granite walking path, benches and cobble swales. The plants went in less than six months before opening and are watered with reclaimed water from the Hyperion Water Reclamation Plant in El Segundo. SCE and the city agreed in 2022 to turn the site into a park, and the late Mayor Bill Brand led that effort. The council named the park for him in July.
Light described it as a native-plant park "that would lead down eventually to the wetlands at the AES site," and said the rest of the lot, running toward Francisca Avenue, could become more park space. For now, the old AES power plant building blocks most of the ocean view from the path, leaving a narrow slice of water. "We thought this would be a good place to plant the flag and show what the future can be like," Light said at the opening, per the Daily Breeze. Easy Reader News covered the dedication in August.
Where Small Gets Contested
Seaside Lagoon shows the downside of going small. Work to revive it began with the city's waterfront amenities plan in 2021. By 2024, the council and Harbor Commission had approved a multi-phase design with a two-story lifeguard and operations building, a separate lap-swimming facility, fire pits and barbecue areas. Then regulators pointed out how expensive it would be to lay groundwork for every phase at once, so city staff cut the plan back to move faster, the Daily Breeze reported.
The current plan has a concrete bottom with a shallow sand area for play, a new water slide, a fountain and splash features, lap-swimming buoys in the deep end, a luau shelter and new landscaping. According to Elizabeth Hause, the city's waterfront and community services director, the lagoon will be filled with potable water instead of saltwater, and the deep end will be 5 feet instead of 10. In September the council voted unanimously to submit a coastal development permit application to the California Coastal Commission, and the city has started looking for money for the later phases.
The Harbor Commission had asked the council to go back to the 2024 plan. Commissioner Leslie Chrzan argued that the saltwater, the sandy bottom and the deep water are what make the lagoon unique. Light framed it as a question of momentum.
"This is the closest we've ever gotten to doing something to revitalize the facility."
The same approach that got the sign rebuilt and the park planted is behind the lagoon plan too. Staff cut the scope to keep costs down and speed up the revamp, and the plan still needs a coastal development permit. The lagoon is where residents can see what that trade costs.
| Project | Where | How it moved | Where it stands |
|---|---|---|---|
| King Harbor gateway sign | Marina entrance | Consent calendar, Aug. 4 | Replacement due by November |
| Former Fun Factory | 123 International Boardwalk | Consent calendar, July 21 | Negotiating agreement with Level Up; no lease yet |
| Bill Brand Gateway Park | Herondo St. and PCH | 2022 SCE agreement | First half open since July 28 |
| Seaside Lagoon | King Harbor | Unanimous council vote, September | Permit application headed to the Coastal Commission |
Sushi on the Boardwalk, and the December Dates
The newest food on the harbor is also small. South Bay Sushi Club is a weekend pop-up inside Scholb on the Water at 160 International Boardwalk. It serves sushi and omakase next to Scholb's local beer, Friday through Sunday, according to The South Bay Club. The Infatuation added it to its Los Angeles listings in early September. It's a few doors from the empty Fun Factory.
The rest of the season's dates are set:
- Veterans Day Tribute: Wednesday, November 11, 1 p.m., on the city calendar.
- Riviera Village Holiday Stroll: Thursday, December 3, 5 to 9 p.m., with Santa, the Grinch, a carousel, shops open late and street closures, per the Riviera Village Association.
- King Harbor Holiday Boat Parade: Saturday, December 12. The paddle craft parade runs 3:30 to 5 p.m. and the boat parade 5:30 to 7 p.m., under a "Celebrating 250 Years" theme. The pier concert time is still TBD on the parade site.
If the sign crew finishes on schedule, boats in the December 12 parade will pass under the rebuilt arch, with the new logo where the sailboat used to be.
Whether you're thinking about a home near Herondo Street or along the International Boardwalk, or just want to know how these harbor projects play into what your place is worth, Jenny Morant Group follows every council vote and opening around King Harbor. Start with your instant home valuation, and we'll walk you through which waterfront changes matter for your block.
Purchase Price & Mortgage Comparison Calculator
Compare today's costs vs. a future purchase.
Enter a positive or negative percentage to see impact.
DISCLAIMER: THIS TOOL IS INTENDED FOR INFORMATIONAL AND ILLUSTRATIVE PURPOSES ONLY. THE RESULTS PROVIDED ARE ESTIMATES BASED ON THE INFORMATION YOU PROVIDE, AND ACCURACY IS NOT GUARANTEED. YOU SHOULD NOT RELY SOLELY UPON THE CALCULATIONS IN THIS TOOL AND ARE ADVISED TO CHECK ALL AMOUNTS AND CALCULATIONS PROVIDED. WE ASSUME NO LIABILITY FOR ANY FINANCIAL DECISIONS MADE BASED ON THE INFORMATION PROVIDED BY THIS TOOL.
THE LOAN TERMS YOU MAY RECEIVE MAY BE DIFFERENT FROM THESE ESTIMATES. LOAN QUALIFICATION, INTEREST RATES, AND PAYMENTS ARE SUBJECT TO CHANGE AND DEPEND ON VARIOUS FACTORS INCLUDING YOUR CREDIT HISTORY, FINANCIAL SITUATION, AND PROPERTY DETAILS. PLEASE CONSULT WITH A QUALIFIED MORTGAGE PROFESSIONAL, MORTGAGE BROKER, OR YOUR BANK TO CONFIRM ELIGIBILITY AND FIND OUT WHAT MORTGAGE PRODUCTS ARE AVAILABLE TO YOU.
PROPERTY TAX ESTIMATES ARE BASED ON AN ASSUMED 1.25% ANNUAL RATE AND SHOULD BE CONFIRMED WITH LOCAL AUTHORITIES.